Santa Clara Street Pavement Rehabilitation - Measure 'B'

Streetscape

Summary

Following completion of the concrete rehabilitation phase in 2014, this final project phase rehabilitated a segment of Santa Clara Street between Carolina Street and Tennessee Street, and Florida Street between Mare Island Way and Sonoma Blvd. with a new layer of asphalt.

Budget: $1.29M Engineer’s Estimate
              $1.05M Construction Contract

Status: Complete

Timeline

  • September 25, 2015 - Advertise for Bids
  • October 15, 2015 - Bid Opening
  • November 17, 2015 - Award Construction Contract
  • March 14, 2016 - Notice to Proceed
  • July 1, 2016 - Work Complete