Marina Maintenance Dredging 2016

Streetscape

Summary

This dredging episode removed approximately 14,000 cubic yards of material from the J Dock area of the Vallejo Marina by the October 15 regulatory deadline.  Shallow sediment was removed from beneath the main J Dock float, and deeper access was provided to some berths and the sewer pump-out.

Budget: $505K Engineer’s Estimate
              $493K Construction Contract

Status: Complete

Timeline

  • May 11, 2016 - Advertise for Bids
  • May 26, 2016 - Bid Opening
  • July 12, 2016 - Award Construction Contract
  • August 12, 2016 - Notice to Proceed
  • October 14, 2016 - Work Complete